How to measure productivity of detailers and draftsmen?

user-image
تم إضافة السؤال من قبل Fouad Lasheen , Design Manager , Khatib and Alami Consulting
تاريخ النشر: 2014/06/26
Fouad Lasheen
من قبل Fouad Lasheen , Design Manager , Khatib and Alami Consulting

My Dear Sir, There is no relation betwen  constriction and drafting in these regards, you can draft a small villa prototyped for1000 units. However drafting time may take only2 or3 days, and the project may last for years

مستخدم محذوف‎
من قبل مستخدم محذوف‎

You can measure the productivity of Draftsmen using some units, like detailed tons of construction per week/month or completed drawings per week/month, but didn't forget about construction complexity factor. Etalon of the measure you can define via experience.