Name the curve use to monitor the progress during construction phase of a project?

user-image
تم إضافة السؤال من قبل Ashfaq Hussain , Dy. Chief Engineer , MCC Resources Development co.
تاريخ النشر: 2014/07/05
Ehsan ul Haq Saif Ali
من قبل Ehsan ul Haq Saif Ali , Senior Project Engineer , Almarai

S curve is normally used to monitor thr progress

Ali Harin
من قبل Ali Harin , General Manager , Harinco For Contracting And Trading Company

Thank you dear Ashfag Hussain  for inviting me to participate in answering your

valueble question , During the construction phase of the project  you can use the curve: cost-time

in which you can have general idea about the budget and the cash flow through all the stages of the project from start , intermediate and to the end of the project

Thank you

Best regards

Eng. Ali Harin

Joao Pereira
من قبل Joao Pereira , Project Engineer - Project Management , Saudi Aramco

You can use the S-curve, comparing the Target S-curve and Actual S-curve reveals the progress of the project over time.

i rather use Earned Value, in my opinion has more possibilities and it's better to forecast.  