ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What do you do if the customer does not pay the current milestone payment ?

<h3>You agreed to have4 partial payments after4 major milestones in the project .</h3> <h3>They paid the first2 then refused to pay the third and said we will pay it at the end of the project</h3> <h3>1- Negotiate but never hold the project</h3> <h3>2- Negotiate but if the customer does not pay after2 weeks hold the project .</h3> <h3>3- Stop the project and go to legal to take actions</h3> <h3>4- Other decision .</h3>

user-image
تم إضافة السؤال من قبل Mohamed Hamdy Kamal Riad , Senior Solution Architect , IBM
تاريخ النشر: 2014/09/25
Jowan Jakoush
من قبل Jowan Jakoush , Information System Manager , Maatouk Group

it depend of the project situation:

- is that payment necessary to fund the project?

- is the customer have any financial problem?

- is the project execution  doesn't agreed?

but in general i refer to the first choice you suggested :"negotiate but never hold the project"

Ramendra Sunder Sinha PMP
من قبل Ramendra Sunder Sinha PMP , DGM Planning , Gaur Sons Limited

Refer the payment schedule and other terms & conditions in the Contract Document. Then refer to the legal terms & conditions for settlement of disputes, non-compliance and termination clause. 

First issue a formal written communication to the customer for compliance to the payment schedule.

If he fails to respond, then issue a second formal written communication to the customer for compliance to the payment schedule failing which you shall revoke the legal actions as per the contract.

If he still fails to respond, initiate the legal actions as per Contract terms.  

I believe the best answer is choice1 "negotiate but never hold the project"

Salauddin Mohammad
من قبل Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

At any rate we do not want to lose customer. While coming to payment, this is a common situation that customers doesn't pay on time and further demand a concession, etc. Well, I will go with the option "Negotiate but never hold the project".. 

Only when there is no way to recover money, and there is no way to get any further business in future I would go with the option of taking legal action...

hatem labib
من قبل hatem labib , Quality control manager , MISER consultant

 Negotiate but if the customer does not pay after2 weeks hold the project 

Mohammed Thiab
من قبل Mohammed Thiab , Founder / Chief Consultant , MV Consulting

It depends on what you want from this question.  Are you seeking our professional opinion on how we deal with such situation in real life ?  or is it a PMP exam question  where one answer only would be considered the correct one ? and you want us to help you pick this correct answer ?

Ahmed Shalabi
من قبل Ahmed Shalabi , PMO Manager , Miracles Group

This must be in my risk register, and the action must be predetermined as per the contract.

 

 

 

If not, I will only use sure facts to conduct a cost-benefit analysis, including actual and opportunity costs of using the project's reserve funds against all benefits preserved from maintaining operations.

 

 

I will cease operation once the analysis’s balance fails below my profit margin. Mixing accounts is a taboo in my book.  

Muhammad Saey
من قبل Muhammad Saey , Senior Veterinary Doctor , PAFN Public Autority for Food and Nutrition

Vice versa:

If the customer expect to deliver the project on time but I did not fulfill his requirements, what will he do?

I prefer to negotiate immediately "not within two weeks" to know the root cause of changing the condition of payment, then legal case is the solution with full stop.

Surbhinder S Dhillon
من قبل Surbhinder S Dhillon , Vice President - Marketing & Sales , DALAL STREET JOURNAL - Business & Investment Magazine

1. Connect with the Authority on the project on the customer’s side           a. To check if there is some hitch /they have any problems with your execution           b. To know if it just a temporary fund flow issue

2. In case it’s a temporary cash flow issue, discuss and finalize next date of payment and communicate in writing to them know about your action in clear terms in case the new dates are missed again. It will be of an added advantage in case you could politely add a reason because of which you shall not be in a position to take the project ahead.

3. Update the senior managers associated with the project in your organization know about it and take their opinion on the risks involved, future impact on your business, customer’s past dealings with your company and any news about your customer in the market.   

hossam azzam
من قبل hossam azzam , Fast food restaurant,s manager. , alexandria-egypt

I will take the option1

 Negotiate but never hold the project

aloke chakravartty
من قبل aloke chakravartty , Managing Director , Ural India Ltd

All the comments are on how to handle the problem. The problem is in not assessing the credit ability of the customer before giving credit. If you fail there you have many options left to you which takes time and money which should be avoided.

Dr Aloke Chakravartty, MBA

المزيد من الأسئلة المماثلة