ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Estimated time required in normal conditions complete an activity is -. ?

<p><strong>(a)Pessimistic time</strong></p> <p><strong>(b)Optimistic time </strong></p> <p><strong>(c)Most likely time </strong></p> <p><strong>(d) None of these. </strong></p> <p> </p>

user-image
تم إضافة السؤال من قبل VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.
تاريخ النشر: 2014/10/17
Nemani Kumar
من قبل Nemani Kumar , Sr. Management GM Projects , Unitech

answer is C Most likely time because while calculating grant chart or PERT the normal time means the expected time calculation for which the activity will probably complete so in normal condition it can be called even expected time = (a +4m+b)/6

 

Optimistic time: a

Most likely time: m=normal time also

Pessimistic time: b

khalid Hassanien
من قبل khalid Hassanien , Financial Manger , Alrwania Ltd

(c) Most likely time 

 

Bassem Al Fakih
من قبل Bassem Al Fakih , business operations manager , Dikken el Mazraa

I believe its (c) the most likely time you have given for the task to be finished give or take; at normal conditions you can estimate the time you need to finish the task in hand.....at normal conditions optimism and pessimism are not in need. Extreme conditions taken external or internal factors for a task to be completed under the pessimistic time or optimistic time is most probably something you cant control.

Muhammad Masood
من قبل Muhammad Masood , Regional Director Sales , TCS (Pvt) Ltd

I would say C. 

Mohamed Khaled
من قبل Mohamed Khaled , Head of Planning & Lubrication , Heidelberg Materials

C

Raafat Sallam
من قبل Raafat Sallam , Organizational Development and Training Consultant , Training Centers, Marketing Organizations.

Non of them it isEquation as Mr. Ayoub Tartir.

Omair Abduljaleel Ali Al-Quliey
من قبل Omair Abduljaleel Ali Al-Quliey , Design Engineer , Quliey Office for constructions

Of course i will choose #C# because when we work that's the best time in life after The worship of God..

with my regard..

Sreeram Kashichenula
من قبل Sreeram Kashichenula , Executive Director , Radiance Precision Industries Pvt Ltd

(d) None of these. Estimated time = [Optimistic Time + Pessimistic Time +4 x Most Likely Time]/6

hossam azzam
من قبل hossam azzam , Fast food restaurant,s manager. , alexandria-egypt

Thanks for the invitation

Well...about me  i would say the option  (C) Most likely time

sumin madambikattil
من قبل sumin madambikattil , Senior Planning Engineer- Jeddah Metro , Hyder Consulting International ( Now Arcadis )

Answer . d None of these 

Mean time = (Tp+To+4Tm)/6