  • If comes out form batch plant then shall be Max 160 degree centigrade. 155 is more siutable
  • temprature at time of placing shall be 140 to 145 gives better compaction resuolt. First two to four passes shall not be less than 140 for initial rolling
  • Final rolling temprature shall not be less than 98 degree to get better compaction

remon mekawy
من قبل remon mekawy , Service team leader , east

it is between 150 and 160 c

Sheik Mohideen
من قبل Sheik Mohideen , Factory Manager , Duproof LLc

You have to find out viscosity of binder at different temperature.. From the temperature at which viscosity meeting mixing viscosity we need to follow that temperature.