ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Explain how you can recover your plan in case that you find it now matching the actual plan.

user-image
تم إضافة السؤال من قبل Hani Alfe , Technial office section head - welding & painting & civil works supervisor , Archirodon
تاريخ النشر: 2014/11/19
Zain ul Abdin
من قبل Zain ul Abdin , Project Planning & Control Manager , Redco International Trading and Contracting

For this purpose a baseline is saved so that it is always available for reference and comparison. When the project is updated its current status is as per the actual position and the remaining portion shows the probable completion of activities as per the links established for baseline schedule. If the project is being delayed, the links can be revisited, lags can be reduced and/or the duration of activities can be reduced wherever possible by increasing the resources. 

المزيد من الأسئلة المماثلة