من قبل
Ali Harin , General Manager , Harinco For Contracting And Trading Company
Thank you dear PRAMOD for your valuable question , the stage of creating the work break down structure (WBS) , is the essential step in applying primavera P6 to any project that is to be managed by the program.
So the comparison by WBS between similar projects in the same organization will be in responsible manager , the number of the main divisions of the WBS in the structure frame and the type and number of activities in each WBS division , Also can be compared by budget and spending plan. .