If other people ( such as planners) make activity estimates(time, cost, resources), then what is the project manager role in estimating processes?

user-image
تم إضافة السؤال من قبل Samir Sewelim , Senior Project Manager , Kafaat& Mehwar al benaa
تاريخ النشر: 2014/11/19
MOHAMED GALAL
من قبل MOHAMED GALAL , project manager , saber for contracting

 

    • Provide the team with enough information to properly estimate each activity.

    • Let those doing the estimating know how refined their estimates must be.

    • Complete a sanity check of the estimates.

    • Prevent padding-adding more time and cost to estimation when no information available )

 

Samir Sewelim
من قبل Samir Sewelim , Senior Project Manager , Kafaat& Mehwar al benaa

In addition to the answer above . Project manager ensures that any assumptions created during estimating should be recorded for review . Project manager formulates reserves.