What should be done by the project manager to ensure that all work in the project is included?

<p>a) Create a contingency plan</p> <p>b)  Create a risk management plan</p> <p>c) Create a WBS </p> <p>d) Create a scope statement</p>

user-image
تم إضافة السؤال من قبل Rifat Qumar , Assistant Front Office Manager , Pearl Park Hotel
تاريخ النشر: 2014/12/13
Basit Ali
من قبل Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

c) Create a WBS 

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The correct answer is (C) Create a WBS.

Dhawal Thakkar
من قبل Dhawal Thakkar , Senior Engineer Projects , TDK Corporation

The Correct I would for it is C. " Create a Work Breakdown Structure" 

MALIIK SOHAIL ABBAS
من قبل MALIIK SOHAIL ABBAS , ACCOUNTS MANAGER , AL RAWDAH GREEN SWEET WATER

option c is the correct

LABIB KOOLI
من قبل LABIB KOOLI , Director of the Sectoral Center for Training in Hotel Technologies at Southern Hammamet , Tunisian Vocational Training Agency (ATFP)

Yeah that is the Work Breakdown Structure 

 WBS allows to break a project into manageable units by all team members, each level of the WBS for deepening the details of the tasks to final level: the concrete tasks to perform .

VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
من قبل VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

Option: c) Create a WBS

Amir Ali Muhammad Ramzan
من قبل Amir Ali Muhammad Ramzan , Accounts Officer , Vision Television Network (Pvt) Ltd.

BY Creating WBS statement

Emad Mohammed said abdalla
من قبل Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company

My answer will be c) Create a WBS

Yam Nath Bhattarai
من قبل Yam Nath Bhattarai , A Class Contractor,International Contractor,National Consultant , Full Bright Consultant,Lumbini builders,ItecoNepal,San Jose Nepal

WBS

Khurrum Iqbal
من قبل Khurrum Iqbal , Accountant , Akun Logistic Services

C : Create a WBS (work break down structure).