What should a project manager do or follow to ensure clear boundaries for project completion?

<p>a) Scope verification</p> <p>b)  Completing a scope statement</p> <p>c) Risk management plan</p> <p>d) scope definition</p>

user-image
تم إضافة السؤال من قبل Rifat Qumar , Assistant Front Office Manager , Pearl Park Hotel
تاريخ النشر: 2014/12/14
Emad Mohammed said abdalla
من قبل Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company

My answer will be b)  Completing a scope statement

Entisar Al Faisal
من قبل Entisar Al Faisal , project construction engineer , City of Dearborn

b is the answer

Basit Ali
من قبل Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

b)  Completing a scope statement

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Answer B: Scope statement

Geetesh kumar lalwani
من قبل Geetesh kumar lalwani , Assistant Manager Finance and Treasury , Mawared Energy

d

Yam Nath Bhattarai
من قبل Yam Nath Bhattarai , A Class Contractor,International Contractor,National Consultant , Full Bright Consultant,Lumbini builders,ItecoNepal,San Jose Nepal

scope verification

Karthikeyan Bhaskaran
من قبل Karthikeyan Bhaskaran , Lead Project Engineer , Alucor Ltd

Completing a scope statement : He needs to complete the Scope statements so that every stockholder understand the scope of project.

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

I would do Completing a Scope Statement. (B)

Carasel Dsouza
من قبل Carasel Dsouza , Senior Consultant , Vatchi Technical Services

The Project Manager should ensure in Completing the scope statement so that all the stakeholders of the project are aware of the complete scope of work to be carried out, one needs to ,ark the deliverables milestone too to help in proper mgmt of the project

Scope verification is used for taking formal acceptance from the stakeholders this step should be completed and documented to avoid future conflicts of interest.

Risk Mgmt plan is used in setting up processes to identify project risk and ways how to handle it.

 

Scope definition is breaking down the large deliverable into smaller ones