ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What are the major differences between turn-key project and contract by valuation?

user-image
تم إضافة السؤال من قبل Mayowa Olayiwola Abdul , Project Manager , BETON BAU NIG LTD
تاريخ النشر: 2014/12/17
مستخدم محذوف‎
من قبل مستخدم محذوف‎

1- Turnkey system that would be appropriate in the case of small projects while large and complex projects require more specialized destinations where it is better integrated contracts 

 

2- In turnkey projects we use (union  total Pricing system) "stint price ." And there is no pricing for business items  while contract projects evaluated by giving price to each item as well as duration of performance 

جعفر هندي زين السقاف
من قبل جعفر هندي زين السقاف , "Certified trainer by the Yemeni Engineers Syndicate." , Engineers Syndicate

Turn-key project where the contractor or provider undertakes the entire responsibility from design through completion and commissioning. The client or customer only has to turn the proverbial key to make everything function as it should, where contract by valuation is "Final negotiated or proposed price of a contract".

Mubarak Salahudeen
من قبل Mubarak Salahudeen , Senior Civil/Structural Engineer , Shell Petroleum Development Company

Dear Ola,

This is Salahudeen, please get in touch. My e-mail is .

Regards,

Salahudeen

 

المزيد من الأسئلة المماثلة