ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Will Contractor be entitled to compensation due to prolongation for concurrent delay or has effect concurrently with Employer Delay to Completion?

user-image
تم إضافة السؤال من قبل Abdul Wahab Mohamed Azmy , Chief Accountant , Bahrain Development Centre
تاريخ النشر: 2014/12/18
Vetri Selvan Manikkam
من قبل Vetri Selvan Manikkam , Assistant Manager -Quantity Survey , Larsen & Toubro (Oman) LLC

Employer Delay + No Contractor Delay = Cost & Time

Employer Daley + Contractor Daley =  Depends on the case , Possibly only Time no Cost.

No Employer Delay + Contractor Delay = LD

 

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

If the Contractor incurs additional costs that are caused both by the Employer Delay and concurrent Contractor Delay, then the Contractor should only recover compensation to the extent it is able to separately identify the additional costs caused by the Employer Delay from those cause by the Contractor Delay.

If it would have incurred the additional costs in any event as a result of Contractor Delays, the Contractor will not be entitled to recover those additional costs.

Khalid Mahmood
من قبل Khalid Mahmood , Construction Manager , Crema Constructions Pty Ltd

Guys, it all depends how the contract has been amended and agreed to, however in case of general contract condition If both the delays are concurrent then contractor is not entitled to any EOT and hence nor the cost. Hope this answer your query!

Muhammad samran
من قبل Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

If the project delay due to the employer or contractor negligence  then employer or contractor entitled for compensation but if both are involved in the project delay due to any reason then both are not entitled for compensation.

Sabyasachi Kar
من قبل Sabyasachi Kar , Chief General Manager , LEA Associates South Asia Pvt. Ltd.

While one has to come to the basics to the root cause of delay but concurrent developments are to be viewed and weighted to compensate or not.

Sabyasachi Kar

Kolkata, India

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Always back to basic, what is the reason for the delay and is this a reason for compensation. no more, no less.

المزيد من الأسئلة المماثلة