What is the function of Bill of Quantities (BoQ)?

user-image
تم إضافة السؤال من قبل Abdul Wahab Mohamed Azmy , Chief Accountant , Bahrain Development Centre
تاريخ النشر: 2014/12/21
Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

BoQ may serve as:-

a) A breakdown of the tendered price, with no contractual status, but providing information for the selection from tenderers;

b) A estimate measure of the work for the tendered price, to be used to arrive at a revised contract price once the actual quantities of work carried out are measured. This is the remeasure form of contract.

c) A schedule of rates as the contract basis for valuing variations in the work.

d) A basis for measure of the value of work competed for interim payments.

victor vic
من قبل victor vic , Technical Design , Salini Impregillo / Arail Construction Company

Functions of bill of quantities is the quantity of manpower, materials and equipment to be used in any kind of works in construction or productions works

Mohammed Abdul Hannan
من قبل Mohammed Abdul Hannan , Planning Manager , North 25 (Subsidary of Dubai Holding & Meraas)

Bill of Quantities serves as a basis of detailed breakdown of work scope with unit rates

Muhammad samran
من قبل Muhammad samran , Junior Officer/Project Coordinator , Pakistan Stell Mill

bill of quantities is a document used in tendering process in which incluse the materials, parts, and labor with respect to their costs. It also details the terms and conditions of the construction or repair contract and itemizes all work to enable a contractor to price the work for which he or she is bidding.

Christiaan Gianan
من قبل Christiaan Gianan , Mechanical Engineer and QC Mechanical Engineer , HASTIE SAUDI ARABIA L.L.C

Bill of Quantities serves as a basis of detailed breakdown of work scope, quantity and cost of labor and  materials. In the BOQ this will the basis of contract agreement of the the Client and the Contractor's work description/ scope.

Abdul Wahab Mohamed Azmy
من قبل Abdul Wahab Mohamed Azmy , Chief Accountant , Bahrain Development Centre

BoQ has two primary functions:

(1)   Pre-contract:

BoQ assist contractor in the formulation of their tender.

 

(2)   Post-contract:

BoQ assist in the valuing of progress payment and variation works. During post-contract stage BoQ will facilitate variation orders management by providing a sound, common basis for the valuation and assessment of variations.

The function of a BoQ can further be expanded in enabling the creation of price database which proof to be useful for future estimating and can be interrogated as a financial management tools in construction.

 Though Boq seems to be somewhat important document within the construction industry.

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

For me a BoQ is to determine if a contractor has a correct basis for his quotation, but also to see if a time schedule is relevant.