Which of the following is not true of multi-weighted scoring models?

<p><strong>A) Will include quantitative criteria </strong><strong>B) Will include qualitative criteria </strong><strong>C) Each criterion is assigned a weight </strong><strong>D) Projects with higher scores are considered more desirable </strong><strong>E) All of the above are true</strong></p>

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/01/07
Mohamed Galal Hussein Ahmed Mohamed
من قبل Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

E) All of the above are true

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

After investigating all the answers, yes E.

Omair Abduljaleel Ali Al-Quliey
من قبل Omair Abduljaleel Ali Al-Quliey , مدير لمكتب المهندسين اليمنيين , مكتبي مكتب المهندسين اليمنيين

Thanks En.ALex..

"E"

Vinod Jetley
من قبل Vinod Jetley , Assistant General Manager , State Bank of India

E. All of the above are true is the correct answer.

Ibrahim Hussein Mayaleh
من قبل Ibrahim Hussein Mayaleh , Sales & Business Consultant and Trainer , Self-employed

All the answers are true (E)

Manjusha Mohan
من قبل Manjusha Mohan , Program Manager , Neo Technology Ltd

B) Will include qualitative criteria 

Only quantitative criteria will be considered for which each criteria will be assigned a weight which is used to calculate the total score of a project.

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Yes the correct answer is....................

E) All of the above are true

RAJ DAHIYA
من قبل RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

Option E

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Agree with my colleagues 