ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

You are the Project Manager for XYZ project. The scope of the project has been completed.

<p><strong>You receive a request for a new module to be developed as part of this project. What should you do next? </strong></p> <ol><li><strong>You should approach the Project sponsor and ask her for a new module to be developed as part of this project. </strong></li> <li><strong>You should approach the Senior Management and ask them for a new module to be developed as part of this project. </strong></li> <li><strong>You should send the request to Change Control Board for approval. </strong></li> <li><strong>Since the project scope is completed you should inform the customer that this change cannot be done as part of the project.</strong></li> </ol>

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/01/07
Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

I would contact the Sr. Project Manager to get with the Project Sponsor

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

The scope is done so it has to be treated as a new (Part of the ) Project. I would ask senior management to take it up with the Project Sponsor or ask if I can take it up with her.

Irina Chepel
من قبل Irina Chepel , Personal trainer , Freelancer

3, if not, otherwise4

Basit Ali
من قبل Basit Ali , Director of Engineering , Laverda Suites & Villas / Blue Bay Resorts

Option3

mohamed shaaban ramadan moursi moursi
من قبل mohamed shaaban ramadan moursi moursi , project manager , PEAKS CONSTRACUTIONS & MAINTANANCE COMPANY

Option4

Mohamed Galal Hussein Ahmed Mohamed
من قبل Mohamed Galal Hussein Ahmed Mohamed , Technical Mnager , Fast Building Contracting Co.

4. As the scope is completed, the project is complete. Additional work should be done as part of a new project.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Since scope is completed so I assume the project has already been baselined, therefore the change should go to change control board for approval.

My answer is choice (3) You should send the request to Change Control Board for approval.

Muhammad Shakeel
من قبل Muhammad Shakeel , CAD Design Manager , M/S zeeruk Intl.

The scope of work completed and Time duration for completion of project is also finish so any new assignment should treat as a new Project even this is an additional work of same project in this case i will ask senior management to take it up as a new Module.

 

If the scope of work completed before the planned time schedule and contractor not yet demobilize from site, so any new assignment from client should treat as an additional work of same project in this case i will ask senior management to take it up as a new Module and also send a request to change control Board for approval.

RAJ DAHIYA
من قبل RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

Instead of denying to Customer, You should send the request to Change Control Board for approval hence, option "3" is more appropriate here.

ARUN BENADICK
من قبل ARUN BENADICK , Planning /Scheduling Engineer ( Ksa ) , Eastern Trading & Contracting Company

Option3. You should send the request to Change Control Board for approval.Because scope only completed. Still customer not accepted the Product. So Project is not completed.

المزيد من الأسئلة المماثلة