أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
<p><strong>You receive a request for a new module to be developed as part of this project. What should you do next? </strong></p> <ol><li><strong>You should approach the Project sponsor and ask her for a new module to be developed as part of this project. </strong></li> <li><strong>You should approach the Senior Management and ask them for a new module to be developed as part of this project. </strong></li> <li><strong>You should send the request to Change Control Board for approval. </strong></li> <li><strong>Since the project scope is completed you should inform the customer that this change cannot be done as part of the project.</strong></li> </ol>
I would contact the Sr. Project Manager to get with the Project Sponsor
The scope is done so it has to be treated as a new (Part of the ) Project. I would ask senior management to take it up with the Project Sponsor or ask if I can take it up with her.
3, if not, otherwise4
Option3
Option4
4. As the scope is completed, the project is complete. Additional work should be done as part of a new project.
Since scope is completed so I assume the project has already been baselined, therefore the change should go to change control board for approval.
The scope of work completed and Time duration for completion of project is also finish so any new assignment should treat as a new Project even this is an additional work of same project in this case i will ask senior management to take it up as a new Module.
If the scope of work completed before the planned time schedule and contractor not yet demobilize from site, so any new assignment from client should treat as an additional work of same project in this case i will ask senior management to take it up as a new Module and also send a request to change control Board for approval.
Option3. You should send the request to Change Control Board for approval.Because scope only completed. Still customer not accepted the Product. So Project is not completed.