You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only

<p> after two days of completion of painting of walls. This is an example of</p> <p>a.Lag b.Lead c.Slack d.Float</p>

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/01/07
مستخدم محذوف‎
من قبل مستخدم محذوف‎

Hi...

This is an example of lag...

kevil Vavaiya
من قبل kevil Vavaiya , Civil Engineer , ASCO Consulting Engineers

Answer is A) Lag

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

A: Lag is the amount of time after the completion of the predecessor activity, when the successor activity can start.

mohamed shaaban ramadan moursi moursi
من قبل mohamed shaaban ramadan moursi moursi , project manager , PEAKS CONSTRACUTIONS & MAINTANANCE COMPANY

a.) Lag

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The correct answer is

a. Lag

Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

my choice is a) Lag