The two closing procedures are called:

<p><strong>A. Contract closure and scope verification</strong><strong>B. Close Procurements and Close Project</strong><strong>C. Project closure and product verification</strong><strong>D. Project closure and lessons learned</strong></p>

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/01/08
Ibrahim Hussein Mayaleh
من قبل Ibrahim Hussein Mayaleh , Sales & Business Consultant and Trainer , Self-employed

I believe (B) Close procurments and Close project

Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

  I agree and I have chosen B. Close Procurement and Close Project

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Answer B, just something to know

Vinod Jetley
من قبل Vinod Jetley , Assistant General Manager , State Bank of India

B. Close Procurements and Close Project

RAJ DAHIYA
من قبل RAJ DAHIYA , Project Manager - Energy Optimization , Siemens

Option B is correct !!

mohammadsadiq kadiri
من قبل mohammadsadiq kadiri , Quality Control Engineer , Nesma telecom and technology

As project is completed we close procurements and the project  itself.

Manjusha Mohan
من قبل Manjusha Mohan , Program Manager , Neo Technology Ltd

Project closure and lessons learnt

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

The correct answer is

B. Close Procurements and Close Project