The unique identifiers assigned to each item of a WBS are often known collectively as:

<p>A. The work package codes</p> <p>B. The project identifiers</p> <p>C. The code of accounts</p> <p>D. The element accounts</p>

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/01/08
Ghanendra Mishra
من قبل Ghanendra Mishra , Social Worker , International Organization for Migration

C

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

Code of accounts, so answer C

Vinod Jetley
من قبل Vinod Jetley , Assistant General Manager , State Bank of India

The answer is :

C. The code of accounts

Divyesh Patel
من قبل Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

C. The code of accounts

Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

Based what I have found my answer is A. The work package codes

Each item in the WBS is generally assigned a unique identifier; these identifiers can provide a structure for a hierarchical summation of costs and resources. The items at the lowest level of the WBS may be referred to as work packages, especially in organizations that follow earned value management practices. These work packages may in turn be further decomposed in a sub-project work breakdown structure. Names for work breakdown structure levels: 

  1. Program
  2. Project
  3. Task
  4. Subtask
  5. Work Package
  6. Level of Effort

Ibrahim Hussein Mayaleh
من قبل Ibrahim Hussein Mayaleh , Sales & Business Consultant and Trainer , Self-employed

It should be the code of accounts (C)

مستخدم محذوف‎
من قبل مستخدم محذوف‎

I think it is A

Manjusha Mohan
من قبل Manjusha Mohan , Program Manager , Neo Technology Ltd

Code of Accounts. - this is a project management tool which assigns a code made from numbers, letters or a combination of the two to every item on the WBS of a project.