أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
<p><strong>A. An external event such as a change in government regulation. </strong></p> <p><strong>B. An error or omission in defining the scope of the product. </strong></p> <p><strong>C. An error or omission in defining the scope of the project. </strong></p> <p><strong>D. a and c </strong></p> <p><strong>E. all of the above</strong></p>
All the first mentioned: A, B & C
Answer option : E.
Change requests are made to ensure that the planned outcome of the project is achieved, so answer E
http://www.aiopass4sure.com/pmi-exams/pmi-002-exam-questions/a-change-requests-can-occur-due-to.html
E. all of the above
E. all of the above
Yes, the correct answer is ...............
E. all of the above