أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
Delphi technique.
This communication technique relies on a panel of experts to achieve convergence of opinion on a specific issue by answering a series of questionaires.
B. Delphi technique
The Delphi technique is a commonly used tool to secure expert judgment while initiating a project.
it is called B: Delphi Technique
is the correct answer.
Answer is B
Thank you for the question, but must agree with others as it's not my field of expertise
Answer option (B) >>>>>>>>> Delphi technique
Agree with u; sir.
I agree with all on the Delphi Technique
Opt B
The answer is B
هل تحتاج لمساعدة في كتابة سيرة ذاتية تحتوي على الكلمات الدلالية التي يبحث عنها أصحاب العمل؟