أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
What can be determined from these figures?
A. The project is behind schedule and over cost.B. The project is ahead of schedule and under cost.C. The project is ahead of schedule and over cost.D. The project is behind schedule and under cost.
SchedulePerformanceIndexSPI =BCWP/BCWS=40000/50000=0.8<1
CostPerformanceIndexCPI= CWP/ACWP=40000/30000=1.33>1
Then the answer is D
SchedulePerformanceIndexSPI =BCWP/BCWS=40000/50000=0.8<1
For me answer A
answer d
_______________________________________________________________
D. The project is behind schedule and under cost.
_______________________________________________________________
It's not exactly my field of the expertise
the answer is D
Choice (D)
I will go with answers given by experts.
D. The project is behind schedule and under cost
but i dont now a comtability
and thinks for your invitation