أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
Earned Value of the project is the monitoring of the project plan to show what is already done and how much of the project costs has been spent.
So the answer is (B) Completed work value
Option (B) Completed work value
Most accurate answer is
B. completed work value
Earned Value is an approach where you monitor the project plan, actual work, and work-completed value to see if a project is on track. Earned Value shows how much of the budget and time should have been spent, with regard to the amount of work done so far.
So I would say: answer E: A and B but you also know C and D
Option B
Earned value management (EVM), or Earned value project/performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner.
Therefore I go with Option E ... well that was my original answer and been informed that I am not completely correct ... so I am changing it to Option B
is the correct answer.
the answer is B.