If you have done every possible attempt as a contractor to resolve a major dispute with the client, not to go to court, and

the project is in the handover stage, and you feel it's just a way to get a major cost reduction by the client, what would you do?

user-image
تم إضافة السؤال من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society
تاريخ النشر: 2015/02/13
Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

Best seek an advice from an independent3rd party to understand the consequences of going to court and how would the court role in this case, and before making a decision of taking a big loss.

Vinod Jetley
من قبل Vinod Jetley , Assistant General Manager , State Bank of India

Try and negotiate with  the client. Go for arbitration, if the contract provides.

zafar abbas minhas
من قبل zafar abbas minhas , Freelance Writer , DAILY MASHRAQ

BEST WAY IS TO USE SOME INFLUENTIAL THIRD PARTY TO MAKE HAPPY ENDING ADJUSTMENT OUT OF COURT................ GOOD DAY

Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

I would go for arbitration 

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

I agree with Mr. Jetley and Mr. Al-Yazoeri, a third Party is arbitration, but... try to negotiate with the contractor , so he wind, you win, so the client wins on both ways

VENKITARAMAN KRISHNA MOORTHY VRINDAVAN
من قبل VENKITARAMAN KRISHNA MOORTHY VRINDAVAN , Project Execution Manager & Accounts Manager , ALI INTERNATIONAL TRADING EST.

Sir, A mediator solution-- even go for a deep discount.--some losses are inherent to every kind of business even though we have all the justifications.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

I will spare him resort to the court by his desire

 

After the entry into force of all the friendly methods

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Some good answers are written below, I echo with most of the answers and will add one thing that, whenever there is a conflict the Project Manager need to be impartial to both parties, listen and understand, and explain to parties to have win-win situation..

 

Divyesh Patel
من قبل Divyesh Patel , Assistant Professional Officer- Treasury , City Of Cape Town

Always try to resolves any issues between you and the client before taking it to the court. You always want to keep the positive relationship.