The major steps involved in the process of concreting are as follows:

1. Batching

2. Mixing

3. Transporting and placing of concrete

4. Compacting.

Batching: The process of measurement of the different materials for the making of concrete is known as batching. batching is usually done in two ways: volume batching and weight batching. In case of volume batching the measurement is done in the form of volume whereas in the case of weight batching it is done by the weight.

 Mixing: In order to create good concrete the mixing of the materials should be first done in dry condition and after it wet condition. The two general methods of mixing are: hand mixing and machine mixing.

Transportation and placing of concrete: Once the concrete mixture is created it must be transported to its final location. The concrete is placed on form works and should always be dropped on its final location as closely as possible.

Compaction of concrete: When concrete is placed it can have air bubbles entrapped in it which can lead to the reduction of the strength by30%. In order to reduce the air bubbles the process of compaction is performed. Compaction is generally performed in two ways: by hand or by the use of vibrators.

Elke Woofter
من قبل Elke Woofter , Project Assistant , American Technical Associates

Batching

Mixing

Transport of concrete

Compacting

 

More is to be found a the website listed below:

www.madehow.com/Volume-4/Concrete-Beam-Bridge.html

... simple and inexpensive concrete beam bridge. ... arch bridges of stone and concrete, ... Process Because each bridge is uniquely designed ...

www.coolinterview.com/interview/60093

What are the steps involved in the concreting process, explain? ... The process of measurement of the different ... The concrete is placed on form works and should ...

 

Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

1. Batching

2. Mixing

3. Transporting and placing of concrete

4. Compacting.

I support the explanation of Elke and Muhammed.

Ali Mohamed Ahmed
من قبل Ali Mohamed Ahmed , site engineering , شركة مقاولات

I agree with Mr.Shakeel  answer ... Thank You

Muhammad Khalil
من قبل Muhammad Khalil , Chief Engineer (Civil) , Water and Sanitation Services Mardan

Support the experts answers. I will add that brick masonary in super structure or below plinth level is carried out in1:5 or1:6 ratio.

Mahmoud Zaher Tarakji
من قبل Mahmoud Zaher Tarakji , مدير , أوال جاليري

I agree with MRS ELKE WOOFTER

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Batching of Concrete

 

 

It is the process of measuring concrete mix ingredients either by volume or by mass and introducing them into the mixture. Traditionally batching is done by volume but most specifications require that batching be done by mass rather than volume. 

 

Mixing of Concrete

 

The mixing operation consists of rotation or stirring, the objective being to coat the surface the all aggregate particles with cement paste, and to blind all the ingredients of the concrete into a uniform mass; this uniformity must not be disturbed by the process of discharging from the mixer.

 

Compaction of Concrete

Once the concrete has been placed, it is ready to be compacted. The purpose of compaction is to get rid of the air voids that are trapped in loose concrete.

 

Wolf Klaas Kinsbergen
من قبل Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

For me is number1 : designing and calculating