CPM Method---------------------
Thanks
Method of critical path in project management in a thermal power project with running operations.
Engineering, Procurement, Manufacturing, Site Mobilization, Civil, Structural, Erection of static and Rotary equipments, Electrical, Instrumentation (including loop and function checks), Pre-commissioning, Commissioning & Startup.
Ensure Feed/ Fuel and utilities are provided in time to carry out the Pre-Comm activities.
I believe the best way to insure productivity in any project is to have a good planned to carry out your planned production
enough in your budget ...
a good supply/supplier of materials needed (on time and on hand inventory)... production never should stand still .. so have a good Purchasing team which gets you what you need in a timely manner for a good price...
enough man power to carry out the work
1. Erection Activities
2. Pre Commissioning Activities
3. Commissioning Activities