  • The Five major levels in the manufacturing planning and control system are:

    1. Strategic Business Plan

    2. Production Plan (Sales and Operations Plan) SOP

    3. Master Production Schedule MPS

    4. Material Requirements Plan MRP

    5. Purchasing and Production Activity Control PAC

  • Each level varies in

    • Purpose

    • Timespan (planning horizon)

    • Levelofdetail

    • Planning cycle (Frequency).

  • At each level, three questions must be answered:

    • What are the Priorities --- how much of what is to be produced and when?

    • What is the available Capacity --- what resources do we have?

    • How can DifferencesBetweenPriorities and Capacity be resolved?

Abdou warshan
من قبل Abdou warshan , • مدير إدارة المخازن والنقل , شركة تمكين الدولية للأجهزة المنزلية

The Five major levels in the manufacturing planning and control system are: 

1)  Strategic Business Plan  

2)  Production Plan (Sales and Operations Plan) SOP  

3)  Master Production Schedule MPS  

4)  Material Requirements Plan MRP  

5)  Purchasing and Production Activity Control PAC

Wasi Rahman Sheikh
من قبل Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Well answer given by all the peoples ???????????????

مستخدم محذوف‎
من قبل مستخدم محذوف‎

  1. Strategic Business Plan

  2. Production Plan (Sales and Operations Plan) SOP

  3. Master Production Schedule MPS

  4. Material Requirements Plan MRP

  5. Purchasing and Production Activity Control PAC

Mir Mujtaba Ali
من قبل Mir Mujtaba Ali , Internal Audit Manager , Confidential

1) Business plan

2) Production plan

3) Master production schedule

4) Material requirement plan

5) Purchase and production activity control

Hany Helmy Haleem
من قبل Hany Helmy Haleem , Director of Warehouses , Nasco Automotive

Well Done........................................................

المزيد من الأسئلة المماثلة