أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
While
reviewing submittals, they discover a technical error. One of the commissioning authority's first actions should be to
A. ask the mechanical contractor to correct error
B. ask the supplier to make changes
C. document the error and inform the commissioning team
D. reject the submittal with comments on errors
The commissioning authority should reject the submittal with few comments and ask the submittal to be revised to make it complete. If you give specific comments they only change these comments and it gets your responsibility, so let them do there work!
The governmental commissioning authority should
D. reject the submittal with comments on errors
The correct option is ----------C
document the error and inform the commissioning team
My answer is D) reject the submission with comments on errors ... and have the contractor correct the error
C. document the error and inform the commissioning team
I would choose option (C) document the error and inform the commissioning team
D. reject the submittal with comments on errors
>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>D>>>>>>>>>>>>>>>>>>>>>>