أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A. Work item B. Work package C. Workaround D. Work breakdown structure
I would opt for
C. workaround
as a ..... C. Workaround
Ans >>>>>>>>>>>>>>>>> D. Work breakdown structure
work around.
Work around is the devised response for occurrence of negative events. unlike contingency plans its a reactive response planning rather than proactive as in contingency planning. More, it is designed solely to bypass, not correct, the problem at hand it should not be expected to survive long past the initial discovery of the problem.
Option (c) is correct answer.
The correct answer is (c) Workaround. workarounds are reaponses to problem that develop while project is being worked, they are never planned, as problems being addressed were never anticipated.