ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

During which stage of risk planning are risks prioritized based on probability and impact?

 

a) Perform Qualitative Risk Analysis

b) Monitor and Control Risks

c) Plan Risk Management

d) Identify Risks

user-image
تم إضافة السؤال من قبل Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer
تاريخ النشر: 2015/04/28
Javed Khan
من قبل Javed Khan , Deputy General Manager Marketing and Sales , InSolare Energy Pvt Ltd

it should be Perform Qualitative Risk Analysis as in this stage only we prioritized risk as High and Low based on there probability and impact.

Firstday Jesse
من قبل Firstday Jesse , Sales Representatives , Nigerian Bottling Company Limited Lagos

d) %%%%********0()Identify Risk%%%%%%^#$##%%^&$$

Vinod Jetley
من قبل Vinod Jetley , Assistant General Manager , State Bank of India

^^^^^^^^^^^^^^^^^^^^a) Perform Qualitative Risk Analysis^^^^^^^^^^^^^^

PURUSHOTHAM Chandra
من قبل PURUSHOTHAM Chandra , Senior Financial Analyst , Dell EMC

My Answer is 

>>>>(a) Perform Qualitative Risk Analysis

مستخدم محذوف‎
من قبل مستخدم محذوف‎

I will go with A.

Qualitative analysis and(or) quantitative analysis is the stage that will help in prioritize risk or in other words in ranking risks.

Shaik Mahaboob Subhani
من قبل Shaik Mahaboob Subhani , Strategy IT Head , Annapurna Finance

Risk is always Risk :)

 

Risk Analysis means you are in the Project Planning Stage not in Execution.  Probability/Impact is part of   Qualitative Risk Analysis.

 

Mohamed El Sayed
من قبل Mohamed El Sayed , Senior project manager , Solid Constriction S.A.E.

as an output from perform qualitative risk analysis project document update which include update risk register and prioritize the the risk based on its probability and impact  

Nancy Refai
من قبل Nancy Refai , Health, safety and environmental management Trainer and consultant , Freelancer

a) Perform Qualitative Risk Analysis

NISHA SUKESH
من قبل NISHA SUKESH , Manager , K Raheja Corp

Qualitative Risk Analysis.

Khaled Anwar
من قبل Khaled Anwar , Senior Sales Engineer , "Automotive company''

I think the answer is:  ( a ) Perform Qualitative Risk Analysis

Emad Mohammed said abdalla
من قبل Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company

>>>>>>>>>>> a) Perform Qualitative Risk Analysis >>>>>>>>>>>>

المزيد من الأسئلة المماثلة