What is the difference between performance % complete, physical % complete and schedule % complete?

These are calculated and stored separately in the P6 database.

user-image
تم إضافة السؤال من قبل Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture
تاريخ النشر: 2013/08/05
Ali Harin
من قبل Ali Harin , General Manager , Harinco For Contracting And Trading Company

Thank you Anisuddin for your valuable question.
The three terms are very important in monitoring, controlling and tracking the project progress.
The performance% complete is used when you use the amount of the units consumed as a percentage of the total that is needed to complete the work.
The physical % complete is used when you use the actual measurements of the work done that you use to update the project with,as a percentage of the total amount of the work of the project.
The schedule % complete is used when you use the duration of the work done of the project as a percentage of the total duration of the project to show your stage.
Thank you Best regards

Binil Paul
من قبل Binil Paul , Sr. Planning Engineer , KEO International Consultants

Performance pc is the percentage of units consumed over the total units available Physical pc issued when u update the schedule manually ..u can use I based on yr assumption of progress of the activity Schedule pc is the time consumed over the total time for an activity You may use any of these to analyse the progress of the project

jillan ksr
من قبل jillan ksr , Principal Advisor-Planning and Freelance Trainer , Navig Solution Private Limited

Hi,

Instead of long explanation, i am posting a video of mine that explains difference between performance % complete, physical % complete and schedule % complete

Part 1- https://youtu.be/6Um_XGg0yUU

Part- 2- https://youtu.be/JVG3Bu2kCiw

 

Reagrds,

Nikhil Raj

www.tutomaash.com

+919961654525 whatsapp