ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Finished planning and have begun executing the project when the client asks if you would add some important features to the product of the project.

. How are the triple constraints affected?

  1. Scope and quality would be affected but not cost
  2. Cost must remain constant because resources are limited
  3. Adding features will require additional cost but not time
  4. Time and cost may both be affected

user-image
تم إضافة السؤال من قبل Muhammad Hamid Munir PMP , Senior Project Manager/ System Program Manager , Ericsson
تاريخ النشر: 2015/05/27
Alex Al Yazouri
من قبل Alex Al Yazouri , General Manager , Al Mushref Cooperative Society

4.  Time and cost may both be affected

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Option No.4

--------------------

Thanks

Muhammad Hamid Munir PMP
من قبل Muhammad Hamid Munir PMP , Senior Project Manager/ System Program Manager , Ericsson

Option4 is the Answer for this Question.

Armando Codilla
من قبل Armando Codilla , WAREHOUSE OPERATOR , Macae Rio de Janiero

No 1 - Scope and quality would be affected but not the cost.

Farid Khan
من قبل Farid Khan , Audit Manager Advisory and consultancy –Afghanistan-Pakistan , Baker Tilly Chartered Accountants Firm

  1. Adding features will require additional cost but not time

المزيد من الأسئلة المماثلة