ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The activity is 10 days for which we have completed 5 days but as per the quantity its only 30% in gantt how to show i have done 30 % not 50 %

The activity is for10 days from which we have completed5 days but based on the quantity we have complete only30% of the job now in gantt chart how to show i have done30 % instead of50 %

user-image
تم إضافة السؤال من قبل Mohammad Sadiq Sharief , chief marketing officer , Apple Oral And Dental Pvt Ltd
تاريخ النشر: 2015/05/28
Wessam Ali
من قبل Wessam Ali , MEP Project Manager , British Petroleum

You should use the Schedule performance index to  clarify the value gained (earned) so far:

EV (Earned Value; value equivalent to what actually gained) =3 days 

PV (Planned Value;value that should be gained ) =5 days

SPI (Schedule Performance Index; Percentage completed measured to what was planned)

=3/5=0.6 or60% of the planned quanitities

Faisal Bukhari
من قبل Faisal Bukhari , Project Coordinator , AETCON

Yes use EVM method in which earned value and actual cost is two different quantities

Ahmed Montasser Hasan Ibraheem Farag
من قبل Ahmed Montasser Hasan Ibraheem Farag , Project Manager , Rawafed Tech

Thanks for invitation, and I am really sorry for my late, because I were  had a lot of work.

Mohammad  Hamiduddin
من قبل Mohammad Hamiduddin , Project Manager (Planning & Control) , Linc Digital System Pvt. Ltd.

You should use physical % complete to update your activities progress.