The activity is for10 days from which we have completed5 days but based on the quantity we have complete only30% of the job now in gantt chart how to show i have done30 % instead of50 %
You should use the Schedule performance index to clarify the value gained (earned) so far:
EV (Earned Value; value equivalent to what actually gained) =3 days
PV (Planned Value;value that should be gained ) =5 days
SPI (Schedule Performance Index; Percentage completed measured to what was planned)
=3/5=0.6 or60% of the planned quanitities
Yes use EVM method in which earned value and actual cost is two different quantities
Thanks for invitation, and I am really sorry for my late, because I were had a lot of work.
You should use physical % complete to update your activities progress.