When using programming software in construction projects which are the better activities do you think in general: (a)SS(b) FS (c) F F?

user-image
تم إضافة السؤال من قبل Bader Eldin Elameen , Deputy Executive Manager , Bin Zehefa for general contracting
تاريخ النشر: 2013/08/19
Anisuddin Siddiqui
من قبل Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture

These are the type of relationships between activities and depends upon the situation.
Nothing is good or bad.
We use as the situation demands.

Zaki El-Din Tohamy
من قبل Zaki El-Din Tohamy , Operations Manager , OVM-MENA

I beleive the best activities that has FF relationship as they have no serious dependency for execution on site.
However, In most cases the type of relation is mandatory and not arbitrary.

RAMAMURTHY SRINIVASAN
من قبل RAMAMURTHY SRINIVASAN , DEPUTY GENERAL MANAGER , GODREJ CONSUMER PRODUCTS LTD

Any project depends on the completion of activites in time and FF is more relevant

Bhavin Mehta CCP(CCE), PMP
من قبل Bhavin Mehta CCP(CCE), PMP , Assistant Manager , Larsen and Toubro Ltd

except SF, all relationships are good.