ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The Scope Management section of your project plan document would include information on:?

  1. What type of scheduling software to use.
  2. How to ask for more money for the project.
  3. How risks are to be managed.
  4. Who can suggest changes to the project.

user-image
تم إضافة السؤال من قبل Muhammad Hamid Munir PMP , Program Manager , Ericsson AB
تاريخ النشر: 2015/07/21
ANAND SANGAM
من قبل ANAND SANGAM , Regional Business Manager , Yash Pharma Laboratories pvt ltd

1 Depends on product2 Customer acceptance knowledge in market3 By product experts and team coordination4 Team Leader,Team and Management

Vinod Jetley
من قبل Vinod Jetley , Assistant General Manager , State Bank of India

  • Who has authority and responsibility for scope management
  • How the scope is defined (i.e. Scope Statement, WBS, WBS Dictionary, Statement of Work, etc.)
  • How the scope is measured and verified (i.e. Quality Checklists, Scope Baseline, Work Performance Measurements, etc.)
  • The scope change process (who initiates, who authorizes, etc.)
  • Who is responsible for accepting the final project deliverable and approves acceptance of project scope

So, the answer is "4. Who can suggest changes to the project.?"

Emad Mohammed said abdalla
من قبل Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company

Scope involve getting information required to start a project, and the features the product would have that would meet its stakeholders requirements

all your choices could fit in the answer..............................thanks.

المزيد من الأسئلة المماثلة