This Deal or a New Deal?
By making a claim, the contractor is demanding that the existing deal be enforced. The claim refers to the current construction contract and demands that the owner do something it has already agreed to do. Presenting a change order for the owner’s signature, on the other hand, is the contractor’s request for a new deal. The change order says nothing about whether the owner is living up to the current contract.
They Come in Pairs.
What is confusing is that change orders and claims often occur together. Take the situation where the owner asks for additional work. The contractor performs and the owner is slow to pay for the extras. What should the contractor do? The contractor will typically submit a change order to increase the construction contract price by the amount of the extras. But what if the owner doesn’t get around to signing the change order? Has the contractor made a claim for payment? No. All the contractor has done is suggest the amendment by change order.
Here is the catch: most construction contracts impose time deadlines for submitting claims. The AIA construction contract forms, for example, require claims to be made in writing within21 days after the claim arose. In our situation, the contractor could lose its right to be paid if no claim is made within21 days after the extra work was started. Submitting the change order is not sufficient - a claim needs to be made.
Change orders are not subject to the same deadlines as claims. Some construction contracts may impose no deadlines whatsoever on change orders. After all, the owner and contractor can agree to change the deal anytime they want. Other construction contracts impose stricter deadlines on change orders than on claims. Some contracts, for example, require change orders to be written and signed before the change in work occurs. Under this kind of contract, our contractor would be late on both its claim and its proposed change order!
What is a Contractor To Do?
A few guidelines are in order: