The lift plan is a compilation of documents consisting of but not limited to the ff: Lift calculation plan pick and set plan Load chart crane certificate crane operator certificate rigger certificate ground test certificate certificate of lifting tackles lifting supervisor certificate Record of pre lift meeting attendance these are all contained in the lift plan. The person that will prepare the package is the lifting supervisor and its complexity will depend on the load and number of cranes involved.