What is the best way to handle several projects simultaneously that have the same deadline and that require the same team members?

user-image
تم إضافة السؤال من قبل Peggy Traboulsi Chamoun , Marketing Director , Bayt.com
تاريخ النشر: 2013/04/25
islam khalil
من قبل islam khalil , Technical Manager , iCloudit

Plan your Project , Set projects scope , tasks an dead line, let every one know his role in the project , monitor project using tracking tools , communicate with projects teams , its an art how to utilize your resource and costs.

Alan John Sobritchea
من قبل Alan John Sobritchea , Applications Manager , Integrated Health Information Systems

Managing multiple project is such a daunting task.
But we still need to do the job right.
With the right prioritization and tracking method, you'll do just fine.

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Read over the tasks.  Know your people and what they are capable of.  Assess and match resources to tasks.  Budget project time using a realistic measuring rod based upon chief priorities.  Allocate resources (and people are resources) to specific tasks.  Communicate, communicate, communicate and follow-up.  Confront excuses and dismiss them -- because excuses are the parasites that waste and devour time.  Look for facts, accept honesty, and demand commitment.  Put your name and reputation on it.  Ask your team to put their name and reputation on and in it.  Then get to work focusing on achieving positive and efficient results.

Viorel Dumitrache
من قبل Viorel Dumitrache , general manager , BETA

When projects are needing the same competencies, there is a very high probability that they are quite similar. Therefore, use the solutions found for one of them, also, to the other. Of course, adapting it if the case will be. When time is short, do not try to be very creative, walk on known paths!

Mohammad Tayyab MIRZA
من قبل Mohammad Tayyab MIRZA , CEO , All Cure International Pakistan

You simply handle them like you peel an orange and consume it slice by slice.
It takes the same amount of time,effort and discipline to finish it no matter how you you do it and it is alot less messier .....

Mohamed Basem Hemedh
من قبل Mohamed Basem Hemedh , Siren Projects Eastern Region Manager , Nextel Millennium Telecom Manager

I got one similar before but all projects were related to the same customer and this is more easy to handle because your customer with you and you know about the resources and how the progress is. Also the customer can give you the priority of wich project you can handle if you face lake in resources or one project need more resources.

This situation will be more complicated if each project has a different project because you have to assign resources for each project and you have to give the same priority to each project (impossible :)).

 

So I recommend what I call it : Master project plan which shows you high level of deliverables for all projects in same page.

 

Hazem Salama
من قبل Hazem Salama , Senior Member of Technical Staff , Verizon Communications

You can't! Multitasking has been discredited and from experience it only leads to poor quality work.
Nice read here http://www.joelonsoftware.com/articles/fog0000000022.html

Jaleel Rahman
من قبل Jaleel Rahman , Leasing and Business Development Manager , CCO LLC/Sams Food Stores

Handel the easiest one First so it is out of your way.

Fadi Ramahi
من قبل Fadi Ramahi , Chief Growth Officer , Fulfillment Bridge

Prioritize

Mohammed Rafiq
من قبل Mohammed Rafiq , Business Development Manager , M. M. Badkook Restaurants & Catering Co.

DASHBOARD- As a Project Manager the first thing is to lead by example You yourself must be agile and a super multi tasker.
You will be surprised how the Energy flows

مستخدم محذوف‎
من قبل مستخدم محذوف‎

1. Prioritize  and define Simple, medium and complex for your deliverables within the project. Priority1's,2's and one which have complexity should be addressed first. Get the team bying-sign off.

2. Split the experts vs less experts based on the complexity of deliverables.

3. Delegate  as appropriate and make people accountable. Build a RACI atleast at a high level and highlight that as part of your status report.

4. Do Risk management on a weekly basis. i.e Capture all the Risks and plan for the Responses and keep a track of it on a regular basis.  My experience is that if proper Risk management is done, things can be resolved easily as that's a platform where all your concern which you/project team foresee regarding execution of the vision(plan) can be addressed.Really really important.

Good luck.

 

Abdul Rahiman

PMP,RMP,SP,CSM,ITILv3