ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

The ‘‘fast-tracking’’ method of schedule compression involves: complete the project earlier.?

The ‘‘fast-tracking’’ method of schedule compression involves: a) The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally planned.b) Performing activities in parallel, thereby increasing risk.c) Going on a ‘‘mandatory overtime schedule’’ in order to complete the project earlier.d) Assigning ‘‘dedicated teams’’ to the critical path activities.

user-image
تم إضافة السؤال من قبل Majdi Demaide , Senior Project Manager , Brugg Cables AG
تاريخ النشر: 2015/08/26
Uduakobong Akpoho
من قبل Uduakobong Akpoho , Snr. Project Manager – Engineering, Procurement and Construction EPC , Kudzy Konzult Limited

b) Performing activities in parallel, thereby increasing risk.

اعتماد حسين محمدحسين
من قبل اعتماد حسين محمدحسين , Supervisory Supply Management Specialist , abu alfadil plaza

a ‘‘mandatory overtime schedule’’ in order to complete the project earlier.d) Assigning ‘‘dedicated teams’’ to the critical path activities.

Hamad Al Dossari
من قبل Hamad Al Dossari , Business Developer Manager. , Mind Merge

There are numerous ways or strategies that can be followed to do this, of which the most commonly used techniques are:

  • Fast tracking.
  • Crashing.
  • Resource reallocation.

Fast tracking is a schedule compression technique where we change the logic of the project schedule by overlapping critical activities rather than working them strictly in sequence. 

MARCEL NWAGOR
من قبل MARCEL NWAGOR , o Preparation of

project before the actual time of completion in the schedule.

Kathy Castle
من قبل Kathy Castle , Project Controls Specialist /Forensic Claim Analyst /Consultant , Freelance

Fast Tracking and Crashing are two widely used schedule compression methods.

Although both techniques rely on the critical path, there are significant difference between them. This article is a short guide to schedule compression techniques

Schedule Compression

Krishna   KHASANIS  PMP
من قبل Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Option D appears to be the most appropriate.

Performing activities in parallel is another way of fast tracking though it increases the risk.

Abthullah Ameeru
من قبل Abthullah Ameeru , Senior Planning Engineer , Harinsa Qatar

if it is only follow up with the planned schedule at site,

otherwise just schedule compression is not going to be affect anything in the project.

kareem elmesallamy
من قبل kareem elmesallamy , مهندس تخطيط أول , شركة سالكو

Fast tracking  >>> 1 -   activities sequence should be change as per new obstruction

 

Increasing of Manpower productivity-2

 

-3 focus on activities with total float < or = updating period 

Zahid Ehsan
من قبل Zahid Ehsan , Project Manager / Front End Designer/IOS Apps Designer , Spyko

b) Performing activities in parallel, thereby increasing risk.Fast tracking always increase risk, while crashing do not increase risk as much as fast tracking can.

المزيد من الأسئلة المماثلة