What are the methods to make a project estimation more accurate?

Is there any method or techniques used or is there any steps to be followed for the most accurate project estimation

user-image
تم إضافة السؤال من قبل sarath menon
تاريخ النشر: 2013/08/28
Tanveer Ahmad Niazi
من قبل Tanveer Ahmad Niazi , CEO (Self-employed) , Project Management Training & Consultant

The best method I believe is the bottom-up, but needs experience as Rahul said.

Rahul Raj
من قبل Rahul Raj , MEP Project Manager , Almoayyed Air Conditioning WLL

There is no short cut other than experience.

Mohammad Khirfan
من قبل Mohammad Khirfan , Cost Control Manager , Habtoor Leighton Specon

to increase the accuracy of your estimation the following should be done:

1- Quantity take offs.

2- Project documents and specification to be thoroughly studied.

3- Receive quotations from the vendors for non common items.

4- refer to your procurement rates on previous projects for similar items.

5- cross check the price with previous similar tender submitted and where was your price with reference to your competitors.

6- After project award to have a feed back from the operation team for the cost performance, which is usually done via a Cost Control Department.

wahid zaman
من قبل wahid zaman , Project Manager , Energy & Power Cont. Co. Ltd

To follow bottom up estimation

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Bottom up estimation with expert judgement/advise.

Mohammad Rasiwala
من قبل Mohammad Rasiwala , Senior Estimation and Cost Engineer , Parsons

To make your direct cost estimation as accurate as possible , you will need to do the following

1. Proper quantities (if there is buffer you will need to know the percentages)

2. Accurate wastage factors

3. Current market rates.

4. Productivity and operation norms of major equipments

5. Time Cycles

6. Site visit with your logistics plan.

 

with these tools you can do a proper direct cost estimate.