How can you determine that the project schedule is useful to the project wherein some tasks are not implemented as per the required time frame?

user-image
تم إضافة السؤال من قبل CARLOS CELESIO , Project Architect , D-REKAB Contracting
تاريخ النشر: 2015/09/26
Usman Islam
من قبل Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

by using critical path diagram or in other word network diagram, some activities have lag time which are not on critical path. it wont affect network time frame unless completed before its come on critical path or near to it.

ibrahim alsaeh
من قبل ibrahim alsaeh , Saudi Arabia , special business

by doing gantt chart and check the critical path , 