ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

Is the Contractor eligible for prolongation costs, for the delays attributable to Contractors risk and responsibility in concurrent delay situation?

 

How he can claim his prolongation costs concurrent with the Employer delay

user-image
تم إضافة السؤال من قبل SAJI POLACHIRA , Commercial and Contracts Manager , TC Consultancy
تاريخ النشر: 2015/10/15
Parthiban Kothandapani
من قبل Parthiban Kothandapani , Quantity Surveyor , A Reputed Construction Company.

First no EOT can be given for Concurrent delays. Some how If the contractor awarded EOT along with concurrent delays then the contractor have a chance to claim his prolongation cost in accordance with contractual documents.

 

المزيد من الأسئلة المماثلة