ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

which of the following is the best management tool to determine the longest time the project will take?(WBS-Bar chart -Network diagram-Project charter

user-image
تم إضافة السؤال من قبل AHMED SALAH , MEP Projects Manager , CSC Consultant
تاريخ النشر: 2013/04/27
Ahamed Shareef
من قبل Ahamed Shareef , Divisional Head - Quality Assurance , Apollo Tyres Ltd

Network diagram is the tool helpful to identify the longest time project takes. There are many methods, but most familiar is Critical path method.

Detailed activities from WBS must be included in ND with time duration to identify Critical paths/longest durations.

Shejin Varghese
من قبل Shejin Varghese , MEP Engineer , Southern General Services Co. LLC

Critical Path Method Chart, otherwise known as Network Diagram.

Elsayed Ali
من قبل Elsayed Ali , Senior program manager , IBM Middle east and Africa

Network Diagram using critical path method.

ASM Rasheduzzaman
من قبل ASM Rasheduzzaman , Cloud Solution Specialist , Microsoft Bangladesh Ltd.

Network Diagram

مستخدم محذوف‎
من قبل مستخدم محذوف‎

مخطط الشبكه

Adel Raafat
من قبل Adel Raafat , مهندس مشروع , شركة بالمنطقة الشرقيه

Network diagram

kareem kassem
من قبل kareem kassem , Systems Analysis Manager (Middle East and Africa) , IDEMIA

Network diagram

Mohamed Elkhatim Hamada
من قبل Mohamed Elkhatim Hamada , Supply Chain Manager , Central Advance Digitech

Network diagram

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Network Diagram using CPM

mohamed mansour
من قبل mohamed mansour , Planning and Controls Lead Engineer (act as: Project Controls Manager) , Arabian Bemco Contracting co. ltd.

Typically, WBS doesn't contain duration.
Project Charter can only give you limitations, not the real time it should take.
On the other hand, Bar chart and network diagram are two effective tools to represent timing: Bar chart can be effective to see how activities/ tasks are flowing, network diagrams can give the relations and interdependencies, but both cant work separately.
Actually, to control timing, you need to make a blend of them both in a way you can see the flow and durations with the relations visible.
For projects with huge numbers of activities you cant do it manually and you cant see all activities or relations at the same time, so you will need a software that have both Network diagrams and Bar charts like Primavera, Ms project,...etc.

المزيد من الأسئلة المماثلة