أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.
A measure of schedule efficiency on a project. It is the ratio of earned value (EV) to planned value (PV). An SPI equal to or greater than 1 indicates a positive condition and a value of less than 1 indicates an negitive condition.