If we have two follow-ups at hand, which of the path’s tasks should be completed on priority,Why ?

a.  Task on the Shortest Pathb.  Task on the Longest Pathc.  Task which is having major problem

user-image
تم إضافة السؤال من قبل Reza Noroozi , Area Sales Manager (West of Iran) , HomaTelecom (Motorola- Lenovo and Apple Distributor)
تاريخ النشر: 2015/12/25
william mesias
من قبل william mesias , Merchandiser , Gulf Union Foods Co.

making order for the item less or not available in the market

Reza Noroozi
من قبل Reza Noroozi , Area Sales Manager (West of Iran) , HomaTelecom (Motorola- Lenovo and Apple Distributor)

in my opinion, the task that is major for you it should be done.

Wael Abdelatty Abdelaziz Fokhier
من قبل Wael Abdelatty Abdelaziz Fokhier , Merchandising Manager , ASK Clothing Company

c.  Task which is having major problem

مستخدم محذوف‎
من قبل مستخدم محذوف‎

Priority is the first come in to our hand or the first in the queue