ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

If the Earned Value of a project is 500, its Actual Cost is 700, and the Planned Value is 600, the project is: Under bud & on time or within bud but delayed?

1)    If the Earned Value of a project is, its Actual Cost is and the Planned Value is, the project is:

a) Under budget and on time

b) Within the budget but delayed

 

c) Under the budget but with a tendency to rise

Over budget and with a delayed schedule

user-image
تم إضافة السؤال من قبل dav sam
تاريخ النشر: 2016/01/02
Zaferullah Sharief, PMP®
من قبل Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option is D) Over budget and with a delayed schedule

 

After calculating SPI and CPI:

CPI =0. (cost performance index)

SPI =0. (schedule performance index)

 

Both the measurement indexes are less than1.0 which means-: project is delayed as per SPI value and cost overrun as CPI indicates.

Binil Paul
من قبل Binil Paul , Sr. Planning Engineer , KEO International Consultants

SPI < 1 = Delayed

CPI < 1 = Over Budget

Srinivasan Rathinamoorthy
من قبل Srinivasan Rathinamoorthy , MEP Engineer , power point llc

try to complete before the date,reduce the manpower

RAFAEL ISASI SIQUEIROS
من قبل RAFAEL ISASI SIQUEIROS , Independent Consultant / freelance , Own

Over budget and most probably behind schedule

Abdelrahman Owais
من قبل Abdelrahman Owais , Sr. Mechanical Engineer UPDA Certified , Electrowatt

Over budget and behind schedule.

المزيد من الأسئلة المماثلة