ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

As a project manager, in approximating costs, you consider the possible causes of variation of the cost estimates, including risks. For your project, which is in the initiation phase, your team has suggested a rough order of magnitude estimate. This could be in the range of (according to PMBOK)?

user-image
تم إضافة السؤال من قبل sardar mardookhy , PMP certified Project manager , MCCI
تاريخ النشر: 2016/01/16
sardar mardookhy
من قبل sardar mardookhy , PMP certified Project manager , MCCI

A) -5% --- +5%

B) -%---+%

C) -%---+%

D) -%---+5%

Ahmed Badri
من قبل Ahmed Badri , Network Field Operation Support Manager , Sudatel Telecom Group

rough order of magnitude should be in a range of+ percent - percent

Masab Alhasan
من قبل Masab Alhasan , site engineer , House of skills company

yes specially from the site manager