What is the double entry for Under Billing or Over Billing found in the chart of Percentage of Completion Method in a construction company?

user-image
تم إضافة السؤال من قبل Mohamed Hakeem Meerashahib , Branch Manager , Sri Lanka State Trading (General) Corporation
تاريخ النشر: 2016/01/29
Mohamed Hakeem Meerashahib
من قبل Mohamed Hakeem Meerashahib , Branch Manager , Sri Lanka State Trading (General) Corporation

Does the following double entry not come in case of under billing?

 

Debit: Due from customers for contract work A/C

  Credit: Progress billing A/C/ Under billing A/C

 

 

Muhammad Saeed
من قبل Muhammad Saeed , Experienced Associate Auditor (Secondment) , Deloitte and Touche (Middle East)

In case of over billing:

 

Assuming the following data:

Cost Incurred  

Contract price  

Progress billing  

 

To rectify this we will:

CREDIT: Progress Billing A/c with

DEBIT: Due to customer A/c with

 

------------------------------------------------------------------------------------------------------------------------

 

In case of under billing:

 

Assuming the following data:

Cost Incurred  

Contract price  

Progress billing  

 

To rectify this we will:

CREDIT: Due from customer A/c with

DEBIT: Progress billing A/c with