ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What is the double entry for Under Billing or Over Billing found in the chart of Percentage of Completion Method in a construction company?

user-image
تم إضافة السؤال من قبل Mohamed Hakeem Meerashahib , Branch Manager , Sri Lanka State Trading (General) Corporation
تاريخ النشر: 2016/01/29
Mohamed Hakeem Meerashahib
من قبل Mohamed Hakeem Meerashahib , Branch Manager , Sri Lanka State Trading (General) Corporation

Does the following double entry not come in case of under billing?

 

Debit: Due from customers for contract work A/C

  Credit: Progress billing A/C/ Under billing A/C

 

 

Muhammad Saeed
من قبل Muhammad Saeed , Experienced Associate Auditor (Secondment) , Deloitte and Touche (Middle East)

In case of over billing:

 

Assuming the following data:

Cost Incurred  

Contract price  

Progress billing  

 

To rectify this we will:

CREDIT: Progress Billing A/c with

DEBIT: Due to customer A/c with

 

------------------------------------------------------------------------------------------------------------------------

 

In case of under billing:

 

Assuming the following data:

Cost Incurred  

Contract price  

Progress billing  

 

To rectify this we will:

CREDIT: Due from customer A/c with

DEBIT: Progress billing A/c with

المزيد من الأسئلة المماثلة