ابدأ بالتواصل مع الأشخاص وتبادل معارفك المهنية

أنشئ حسابًا أو سجّل الدخول للانضمام إلى مجتمعك المهني.

متابعة

What are the minimum propping period of beams and slabs of various spans?

user-image
تم إضافة السؤال من قبل farrukh aziz
تاريخ النشر: 2016/03/10
Mohammed  Ahmed
من قبل Mohammed Ahmed , Sr.Project Engineer , Saudi Electricity Company

It depends. Concrete gains strength at a non-linear rate (Initially high, later low) and at any stage of time, as long as its strength > strength requirements, you don't need any propping. Mostly, during construction, the loads acting on the beams/slabs are 1) Self weight 2) Construction load (or) 3) Weight of upper floor (from the props !) but this is a separate load case

المزيد من الأسئلة المماثلة