____ is action taken to bring rejected items into compliance with product requirements or specifications or other stakeholder expectations?

A) Process adjustments

B) Rework

C) Acceptance decisions

D) Auditing

 

user-image
تم إضافة السؤال من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves
تاريخ النشر: 2016/04/02
مستخدم محذوف‎
من قبل مستخدم محذوف‎

Although Rework seems to be the correct answer ,however,this term is more appropriate for Manufacturing Industry.For Service Industry certain other term may be more important or relevant.

د Waleed
من قبل د Waleed , Management - Leadership-Business Administration-HR&Training-Customer Service/Retention -Call Center , Multi Companies Categories: Auditing -Trade -Customer service -HR-IT&Internet -Training&Consultation

A. Process Adjustment !

 

 

Thank You

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

My answer is Rework, since other options are not correcting the rejections

Vinod Jetley
من قبل Vinod Jetley , Assistant General Manager , State Bank of India

B) Rework>>>>>>>>>>>>>>>>>>>>>>>>>

Wasi Rahman Sheikh
من قبل Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

C) Acceptance decisions<<<<<<<<<<<<<<<<,