What is the meaning of the planning time fence?

A.  It determines the planning period for the planning run 

B.  It determines the period in which the planned orders are to be converted into production orders 

C.  It determines the period in which no automatic changes are to be made to the production plan

user-image
تم إضافة السؤال من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves
تاريخ النشر: 2016/04/06
RAVISANKAR K
من قبل RAVISANKAR K , Senior Consultant , Envecon Global Solutions Private Limited

Planning time fence don't allow any automatic changes (Ex.MRP execution) for the production plan on the determined period

Sathish Prabhu.V
من قبل Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Option C, Not automatic changes in the production plan  in the specified period is the appropriate answer

Wasi Rahman Sheikh
من قبل Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Option B) is answer <<<<<<<<<<<<<<<<<<<<<<

MUBARAK INAYTULLA KHAN
من قبل MUBARAK INAYTULLA KHAN , Procurement Manager , UNIT7 CONTRACTING EST. RIYADH.

B : IS THE CORRECT ANSWER FOR THE ABOVE QUESTION.

georgei assi
من قبل georgei assi , مدير حسابات , المجموعة السورية

B.  It determines the period in which the planned orders are to be converted into production orders 

 